CHECK DAILY ~~~~~~

CALL IN CHANGES ~~~~~~

CHECK DAILY ~~~~~~ CALL IN CHANGES ~~~~~~

FEB 11

TODAYS OBJECTIVE:

  • Secure the remaining trim and complete installation leading to the basement.

  • Identify and install any remaining floorboards.

  • Gather information from Drew regarding the chimney leak and confirm if the issue has been resolved. If the leak has been addressed, proceed with drywall repairs.

  • Assess the materials required for insulation installation and determine if any additional insulation or drywall needs replacement.

  • Complete the shower tile installation, including hardware, and apply grout.

TEAM 1

ANDY ~ RYAN ~ TODD

LOCATION: OSSEO WI

CLIENT: DREW

TEAM

LOCATION:

CLIENT:

FEB 12

TODAYS OBJECTIVE: